Transforming Cancer Care: Project Timeline

2014

July - October
Formal public consultation - Completed

October - November
Evaluate consultation feedback - Completed

Autumn 2014 - Summer 2015
Outline business case - Completed

2015

19th October - 13th November 2015
Exhibition of designs and pre-planning consultation - Completed

timeline-1.jpg

 

2016

Summer 2016
Full planning permission granted by Liverpool City Council - Completed

Summer 2016
Full business case approval - Completed

Video flythrough: Watch now >>

2017

June 2017
Start on site/contract sign off - Completed

July 2017
Haemato-oncology service transferred from the Royal Liverpool Hospital to The Clatterbridge Cancer Centre - Completed

2018

January 2018
First in country to offer Treatment at Work service - Completed

Jan - June 2018
Building of lower ground to level 4 of new hospital - Completed

April 2018
Five additional clinic rooms added to Outpatients Department at CCC-Wirral - Completed

July 2018
New CT scanner at CCC-Aintree - Completed

July - December 2018
Level 5-9 of new hospital to be built

October 2018
Topping out ceremony (installation of the highest structural feature on the new hospital)

December 2018
Roof slab (Level 10)

2019

July 2019
Façade complete

2020

Spring 2020
Planned completion

3 months from contract completion (3 month period)
Trust commissioning period

3 months after handover
Opening date

2020/2021 onwards

Redesign of existing cancer centre in Wirral

timeline-3.jpg